Architectural Desktop 2004 Standard Wall Component Cleanup Priority Numbers
Wall Component Name Priority Comments
Unnamed (Standard Wall) 1 Not a great number to start with - used with elevator
Concrete (including footings) 200  
Concrete Masonry Unit (CMU) 300  
Air Gap (CMU) 305  
CMU Veneer 350  
Precast Panel 400  
Rigid Insulation (Brick) 404  
Wood/Metal Stud 500  
Air Gap (Stud) 505 two odd cases were found
Insulation (Rigid and General) 600 type of insulation tends to vary
Air Gap (Typical) 700  
Brick Veneer (Structural) 800  
Rigid Insulation 804 cases found with Brick Styles
Air Gap (Brick) 805  
Brick and Brick Veneer 810  
Siding 900 didn't find a case of this but sounds good
Metal Panel 1000 didn't find a case of this but sounds good
Stucco 1100 didn't find a case of this but sounds good
Glass 1200 didn't find a case of this but sounds good
Gypsum Wallboard (GWB) 1200 - 1230 Increments of 10, varies when doubled up
Bulkhead 1800  
Casework - Upper 2000  actual component name is "Case Top"
Casework - Base 2010 Full Body without a toe kick
Casework - Counter 2020  
Casework - Backsplash 2030  
Partitions (Bathrooms) 3000 Embeded in Multi-View Blocks
     
Architectural Desktop 3.3 Standard Wall Component Cleanup Priority Numbers
Wall Component Name Priority Comments
Unnamed (Standard Wall) 1 Not a great number to start with
Partitions (Bathrooms) 55 - 80 Embeded in Multi-View Blocks
Concrete 200  
Concrete Masonry Unit (CMU) 300  
CMU Veneer 350  
Brick Veneer (Structural) 400  
Rigid Insulation (Brick) 404  
Air Gap - Brick 405  
Brick Veneer 410  
Air Gap (Stud) 499 two odd cases were found
Wood/Metal Stud 500  
Rigid Insulation 600  
Air Gap - Typical 700  
Gypsum Wallboard (GWB) 1200 - 1230 Increments of 10
Bulkhead 1800  
Casework - Upper 2000  
Casework - Base 2010 Full Body without a toe kick
Casework - Counter 2020  
Casework - Backsplash 2030